Certificate of completed works (form R-1) in Kazakhstan: template and rules

What changed

Added a bilingual filled-in R-1 sample, the certificate for an individual contractor under a civil law (GPH) contract, and what changes in 2027: VAT on licensed medical services rises from 5% to 10%.

Illustration for “Certificate of completed works (form R-1) in Kazakhstan: template and rules”

In short

  • In Kazakhstan the certificate of completed works (akt vypolnennykh rabot) is drawn up on form R-1, 'Certificate of completed works (services rendered)', annex 50 to Finance Ministry order No. 562; the current version of the form dates from order No. 458 of 27 October 2014.
  • Form R-1 does not apply to construction and installation works: a footnote on the form says so.
  • The form has 6 header fields, a table of 8 columns, a block on the customer's materials, a list of annexes, 'handed over' and 'accepted' signatures and the acceptance date.
  • No rule lets a business replace R-1 with its own design: self-designed forms are allowed only for documents whose form is not approved, though extra fields may be added to R-1.
  • Certificates of acceptance of work under contracts are kept for 5 years after the contract expires (item 337 of list No. 279-NK).

A certificate of completed works in Kazakhstan, akt vypolnennykh rabot in Russian and often just "the akt", is drawn up on form R-1, "Certificate of completed works (services rendered)". It is annex 50 to the Finance Minister's order No. 562 of 20 December 2012, and the current version of the form was introduced by order No. 458 of 27 October 2014. With it the contractor hands over and the customer accepts work or services: consulting, equipment repair, marketing, software development, cleaning. The form itself names one exception: it is not used for construction and installation works. R-1 has six header fields, an eight-column table, a block on the customer's materials, a list of annexes and the signatures of both parties with the acceptance date.

For a foreign company used to closing a job with one invoice, the akt is an extra step: Kazakh accounting law records acceptance of work and services on this approved form. Below we translate every field of R-1, show a filled-in example, and explain what changes when the contractor or the customer is abroad. Texts were checked on adilet.zan.kz on 23 October 2026.

When is a certificate of completed works needed?

R-1 is needed whenever a contractor delivers the result of work or services and the parties record acceptance. For the contractor it supports recognising income, for the customer the expense.

Most often the akt closes a contract for the paid provision of services: the contractor, on the customer's instructions, performs actions or carries out an activity, and the customer pays (Civil Code, article 683). This covers communications, medical, audit, consulting and information services, training and tourism. The contractor provides the services personally unless the contract says otherwise (article 684).

A primary document is made at the moment of the operation or right after it (Law on Accounting, article 7(4)). For a long contract this means signing a certificate per stage or per period named in the contract, not one document after a year; the form has a column for the date of performance for exactly that reason.

Early termination has its own logic. The customer may withdraw from a services contract by paying the contractor's actual costs; the contractor may withdraw only by fully compensating the customer's losses, unless the withdrawal is the customer's fault (article 686). If performance became impossible through the customer's fault, the services are paid in full (article 685). In both cases we suggest recording the part already performed in an R-1 certificate, so that both sides have a document to settle from.

A client and a contractor sign two copies of the act

Can a foreign contractor use its own acceptance document?

Not as a substitute for R-1, as far as the law we checked goes. The Law on Accounting allows a business to design its own form, or to use forms of non-residents, only for documents "whose forms or requirements are not approved", and then the document needs seven mandatory details (article 7(3)). For acceptance of work and services the form is approved: it is R-1.

The common claim that "any form can replace R-1" is not supported by the text. What the law does allow is adding extra details to an approved form (article 7(3-1)), such as a project stage, a ticket number or a purchase order reference. For comparison, the payment invoice in Kazakhstan has no approved form, and a self-designed invoice with seven details is what the law requires.

The sources we checked do not address a foreign party directly. Our suggestion: the Kazakh side prepares R-1 for its own records, and the foreign side's report, timesheet or deliverable list can be referenced in column 4 and in the annex line, which the form provides for reports on research, marketing, consulting and other services. A cross-border deal needs a written contract in any case: a foreign trade deal without written form is void (Civil Code, article 153(3)).

What does each field of form R-1 mean?

R-1 consists of a header, a table, a lower block and signatures. The list below follows the text of annex 50 on adilet; we offer no downloadable file, the table below is the template.

Fields of form R-1 under annex 50 to Finance Ministry order No. 562 with English meaning, checked on 23 October 2026
BlockField or column (Russian name)English meaning and what to enter
HeaderIIN/BINidentification number of the party
HeaderZakazchikcustomer: full name, address, contact details
HeaderIspolnitelcontractor: full name, address, contact details
HeaderDogovor (kontrakt)contract number and date
HeaderNomer dokumenta, data sostavleniyacertificate number and date of issue
Column 1Nomer po poryadkuline number
Column 2Naimenovanie rabot (uslug)name of work or services, by sub-type under the specification, assignment or schedule
Column 3Data vypolneniya rabotdate the work was performed, under the double-asterisk footnote
Column 4Svedeniya ob otchetedetails of a report on research, marketing, consulting or other services: date, number, pages, under the triple-asterisk footnote
Column 5Edinitsa izmereniyaunit: hour, service, month, piece
Column 6Vypolneno rabot, kolichestvoquantity performed
Column 7Tsena za edinitsuunit price under the contract
Column 8Stoimostvalue: quantity × price, with a total line
Lower blockSvedeniya ob ispolzovanii zapasovmaterials received from the customer: name, quantity, value
Lower blockPrilozhenieannexes, including reports, number of pages
SignaturesSdal / Prinyal, M.P. twicehanded over by the contractor, accepted by the customer: position, signature, name
SignaturesData podpisaniya (prinyatiya)date the work was accepted

Footnote * on the form limits its use: acceptance of work and services, except construction and installation works.

How do you fill in R-1 line by line?

The rule is that the certificate matches the contract: same parties, same subject, same prices.

  1. Header. IIN or BIN, full names of customer and contractor with addresses and contacts, contract number and date. Number certificates in sequence.
  2. Column 2. Name the work as the specification or schedule does. "Services under the contract" without detail does not show the content of the operation.
  3. Column 3 under the double-asterisk footnote: fill it if the work covers different periods or the performance date differs from the signing date; otherwise it may stay blank.
  4. Column 4 under the triple-asterisk footnote: only if the service has a report, scientific, marketing or consulting. Give its date, number and page count.
  5. Columns 5 to 8. Unit, quantity, price, value and the total.
  6. Customer's materials. If the contractor used the customer's materials, list them with quantity and value.
  7. Signatures and acceptance date. The acceptance date is the day the customer signs.

A sample of the table, with invented names and prices:

Sample R-1 table with columns 3 and 4 filled in, invented amounts
No.ServicesDate performedReportUnitQtyPrice, tengeValue, tenge
1Accounting system setup, stage 1 of the schedule1 to 15 October 2026nonehour248,000192,000
2Market research20 October 2026report No. 3 of 20 October 2026, 18 pagesservice1150,000150,000
Total342,000

Services are paid with their own purpose code; consulting and engineering services, for instance, take KNP 859 in the payment purpose code directory.

What does a filled-in certificate look like in English and Russian?

There is no official English version of R-1, so cross-border teams usually keep the approved Russian field names and add English next to them. The sample below uses invented parties and amounts; IIN/BIN and contacts are left blank.

Akt vypolnennykh rabot (okazannykh uslug) / Certificate of completed works (services rendered) No. 12, dated 31 January 2027

IIN/BIN ______

Zakazchik / Customer: Sample Customer LLP, address, contacts ______

Ispolnitel / Contractor: Sample Contractor IP, address, contacts ______

Dogovor / Contract: No. 3 of 5 January 2027

1. Accounting services for January 2027 · performed 1 to 31 January 2027 · unit: month · 1 × 120,000 = 120,000 tenge

Itogo / Total: 120,000 tenge

Customer's materials used: none. Annex: list of documents, __ pages.

Sdal / Handed over (Contractor) ______ · Prinyal / Accepted (Customer) ______ · M.P.

Data prinyatiya / Acceptance date ______

Column 4 (report) is left out because this service has no report; on the form it stays blank. The Russian-language site version has an online R-1 generator that prints the form to PDF; in English, copy the fields above into your own template without dropping any of them.

What if the contractor is an individual under a civil law contract?

Then the certificate matters even more. Under a civil law (GPH) contract an individual is paid for a result, not for time, and the certificate shows the result was delivered. A run of monthly payments with no certificates makes the arrangement look like employment, and since 7 June 2026 a civil contract with any sign of employment is expressly banned and treated as an employment contract.

For an individual contractor, enter the IIN and full name in the header, describe the actual work in column 2 rather than a job title, and show the fee before withholdings in column 8: the customer, as tax agent, withholds income tax, OPV, VOSMS and social contributions when paying. If the contractor is registered as an individual entrepreneur, the same form is used but no withholding applies.

Who signs, and is a stamp required?

Two people sign: the contractor on the "handed over" line and the customer on the "accepted" line, each with position, signature and name. Who may sign is decided by the head of the organisation or by the individual entrepreneur, and a hierarchy of signing rights may be set (Law on Accounting, article 10).

The stamp question looks like a contradiction but is not one:

  • the R-1 form shows "M.P." (place for the stamp) twice, for the contractor and the customer;
  • since 1 January 2015 private legal entities are not required to have a stamp (Civil Code, article 33(2)).

If an LLP has no stamp, the certificate is signed without it; the mark on the form does not create a duty to order one. We found no law requiring an individual entrepreneur to have a stamp. Details are in do businesses need a company stamp.

Can R-1 be signed electronically, including from abroad?

Yes. An electronic document signed with the digital signature (EDS) of a person authorised to sign equals a signed paper document (Digital Code, article 62(2)). The head of a business may give an employee the right to sign electronic documents, and the employee then signs with their own EDS (article 62(6)).

An EDS equals a handwritten signature only if four conditions are met together (article 49(2)): authenticity is confirmed by a public key with a certificate, the signer lawfully holds the private key, the EDS is used in line with the certificate data, and the certificate was issued by a certification centre accredited in Kazakhstan or by a foreign one registered with Kazakhstan's trusted third party. That last condition decides whether a foreign signatory's e-signature counts. In our reading, a scanned signature or an image of a stamp in a PDF does not meet the definition. How a business obtains a Kazakh key is covered in digital signature for businesses.

Paper copies of electronic primary documents are needed for other parties and on request of state bodies (Law on Accounting, article 7(6)), but tax inspectors may not demand paper copies of documents registered in the ESF system (Tax Code, article 206(2)).

What taxes follow the certificate?

If the contractor is a VAT payer or, for example, works on the simplified regime, it must issue an ESF (electronic tax invoice) no later than 15 calendar days after the sale (Tax Code, article 493(1)); the term is explained in the glossary entry ESF. The akt and the ESF are different documents and both may be needed.

When the contractor is a non-resident, the Kazakh customer pays VAT for it on the services bought, even if the customer is on the simplified regime, and such purchases count toward the VAT registration threshold. See VAT in Kazakhstan in 2026. Payments to a non-resident may also be subject to income tax at source, explained in corporate income tax for non-residents.

What changes for certificates in 2027?

Form R-1 itself does not change; on 16 November 2026 the 2014 version is in force. The figures around it do.

VAT and ESF terms around a certificate of completed works, 2026 and 2027
Item20262027
Standard VAT rate16%16%
VAT on licensed medical services5%10%
ESF deadline after the sale15 calendar days15 calendar days

The reduced VAT rate for licensed medical services, medicines and medical devices rises from 5% to 10% on 1 January 2027 (Tax Code, article 503(2)). Clinics closing work around the turn of the year should fill in column 3, the performance date, so the period of the services is clear.

Which mistakes in a certificate cause trouble?

Errors in certificates usually surface during a tax audit or in a payment dispute.

Mistakes in a Kazakh certificate of completed works R-1: symptom, cause and fix
SymptomCauseFix
R-1 used for a facade repair with installation worksthe form does not apply to construction and installationdo not use R-1 for such works
A service cannot be proven in an auditcolumn 2 says "services under the contract"describe the work by assignment or schedule
Certificate signed in December for October workno performance datefill in column 3 under the double-asterisk footnote
A consultant's report is not linked to the certificatecolumn 4 empty although a report existsenter the report date, number and pages
A figure in a signed certificate corrected by handcorrection without agreementcorrect only with consent of the parties, same signatures and the date
A foreign contractor sent only an email confirmationacceptance not recorded on the approved formprepare R-1 and reference the contractor's report in column 4

Corrections to primary documents, other than cash and bank documents, are made only with the agreement of the parties to the operation, with signatures of the same persons and the date (Law on Accounting, article 7(7)).

How long are certificates kept?

Documents on acceptance of work under contracts are kept for 5 years after the contract expires (item 337 of list No. 279-NK). For primary documents in general the sources set periods differently:

  • Tax Code, article 206(3): until the tax limitation period expires, but not less than 5 years;
  • list No. 279-NK, item 267: 5 years, subject to an audit.

Where they differ, apply the longer period. For a long services contract the item 337 period starts only after the contract ends.

Kazakh terms used on this page, such as BIN, IIN or EDS, are explained in the glossary. Whether an activity code allows the simplified regime is covered in which OKED codes are allowed on the simplified regime, regional business centres in the regions section, and data on small business in ZhasPro research.

What next

Frequently asked questions

What is the official form of the certificate of completed works in Kazakhstan?
Form R-1, 'Certificate of completed works (services rendered)', annex 50 to Finance Minister's order No. 562 of 20 December 2012. The current version of the form was introduced by order No. 458 of 27 October 2014, and the order was in force on adilet.zan.kz on 23 October 2026.
Can the certificate of completed works be drawn up in free form?
No rule expressly allows replacing R-1 with your own form. Article 7(3) of the Law on Accounting lets a business design a form for documents whose form is not approved, and for acceptance of work and services the form is approved. Extra details may be added to R-1.
Is there an official English version of the certificate of completed works?
No. Form R-1 is approved in Russian and Kazakh (where it is coded Zh-1). A bilingual document is common in cross-border deals: keep the approved Russian or Kazakh fields and add the English wording next to them, as in the sample on this page. Adding extra details to the approved form is allowed (Law on Accounting, article 7(3-1)).
Does form R-1 work for construction?
No. The footnote to form R-1 excludes construction and installation works: the form is used for handing over and accepting completed work and services other than construction and installation.
Can a foreign party sign the certificate electronically?
An electronic document signed with the digital signature (EDS) of an authorised person equals a signed paper document (Digital Code, article 62). The EDS counts as a handwritten signature when its certificate comes from a centre accredited in Kazakhstan or from a foreign centre registered with Kazakhstan's trusted third party (article 49).
Does the certificate need a stamp?
Form R-1 shows 'M.P.' (place for the stamp) twice, but an LLP and other private legal entities have not been required to have a stamp since 1 January 2015 (Civil Code, article 33(2)). Without a stamp the certificate is signed without one. We found no law requiring an individual entrepreneur to have a stamp.

Sources

Figures on this page were checked against these documents. Spotted a mismatch? Tell the editors.

  1. Finance Minister's order No. 562 of 20 December 2012, annex 50: form R-1 (as amended by order No. 458 of 27 October 2014) · checked 23 October 2026
  2. Law of Kazakhstan No. 234-III of 28 February 2007 on Accounting and Financial Reporting: articles 7 and 10 · checked 23 October 2026
  3. Civil Code of Kazakhstan (General Part): article 33(2) (stamp), article 153(3) (foreign trade deals) · checked 23 October 2026
  4. Civil Code of Kazakhstan (Special Part): articles 683 to 687 (paid provision of services) · checked 23 October 2026
  5. Digital Code of Kazakhstan No. 255-VIII of 9 January 2026: articles 49 and 62 (digital signature, electronic document) · checked 23 October 2026
  6. Tax Code of Kazakhstan No. 214-VIII of 18 July 2025: article 206 (storage, paper copies), 208 and 493 (ESF), 449 (VAT on services from non-residents), 503 (VAT 16%; medical 5% in 2026, 10% from 2027) · checked 25 October 2026
  7. List of standard documents with storage periods, order No. 279-NK of 17 June 2025, items 267 and 337 · checked 23 October 2026